Updated Commercial Development Plan for North America’s First Lithium Brine Production Facility

by admin February 6, 2025
February 6, 2025
Updated Commercial Development Plan for North America’s First Lithium Brine Production Facility

Arizona Lithium Limited (ASX: AZL, AZLO, OTC: AZLAF) (“Arizona Lithium”, “AZL” or “the Company”), a company focused on the sustainable development of two large lithium development projects in North America, the Prairie Lithium Project (“Prairie”) and the Big Sandy Lithium Project (“Big Sandy”), is pleased to provide a progress update for the commercial scale proof of concept facility at Pad #1 and further outlay the development plan for the Prairie Project. The Prairie Project will be put into production across three phases of development. Phases I, II, and III represent the methodical steps being taken to cost-effectively bring the project into production while minimising the risk associated with commercialising a first-of-its-kind process.

HIGHLIGHTS

  • Updated strategic phased development plan has been implemented for the Prairie Lithium Project.
  • Phase I will see the Prairie Lithium Project go into production at Pad #1 using a commercial-scale DLE unit capable of producing 150tpa of Lithium Carbonate Equivalent (LCE).
  • To get into production, only AUD35m (USD22m) required to spend on Phase 1 CAPEX.
  • Non-dilutive capital initiatives currently being considered with multiple potential strategic partners completing extensive due diligence on the Prairie Lithium Project, in addition to existing Government grants and loans being considered as well as traditional debt financing solutions.
  • First commercial production marks the first Company in North America to reach this milestone.
  • De-risking by a commercial scale proof of concept allows production to be increased by rapid replication of the process at Pad #1.
  • Construction work will commence at Pad #1 in Q2 2025.
  • Phase 2 will immediately expand the facility with additional commercial-scale DLE units. Additional units can be rapidly deployed to increase production at Pad #1. Phase III will see the Pad design replicated across the already drilled and de-risked Pad #2, and Pad #3. Additional Pad locations are also being finalised in 2025.
  • Grey Owl Engineering has been engaged for facility engineering, procurement, and construction (EPC). Grey Owl is a leading Western Canadian oil & gas facilities engineering company.
  • The Prairie Lithium Project in Canada is perfectly positioned to feed battery-grade lithium carbonate into the mature Asian battery market. Battery-grade samples produced from the Prairie project are currently being distributed and tested in Asia.1

Phase I will see the project go into production at Pad #1 using a commercial-scale Direct Lithium Extraction (“DLE”) unit capable of producing 150 Tonnes Per Annum (“TPA”) Lithium Carbonate Equivalent (“LCE”). The lithium produced will be used to de-risk end market opportunities where battery-grade samples are currently being tested by interested groups in Asia. Phase I will process brine at a rate of approximately 1,000m3 per day. It is critical to process raw brine at this commercial scale to de-risk the temperature, pressure and chemical constituents of the brine while feeding a commercial scale DLE unit 24 hours per day, 7 days a week. A video rendering of Phase I at Pad #1 has been prepared and can be viewed here: https://youtu.be/mUNExsUBjfo

This will represent one of the world’s largest DLE facilities and provide the guidance required to scale up production cost-effectively across the Prairie Project shortly thereafter. Upon commissioning and operating at this scale, the Company will have significantly de-risked the process and proceed to Phase II.

Phase II will see the immediate expansion of production on Pad #1. Phase II expansion will highlight the benefits of modularised scale-up as additional commercial-scale DLE units will be rapidly deployed. Additional wells will also be drilled to maximise production from Pad #1.

Phase III will see the replication of the wells and facility at Pad #1, applied to Pad #2, Pad #3 and additional Pads that are currently being identified.

Arizona Lithium Managing Director, Paul Lloyd, commented:“We are excited to share additional details about our plans for the Prairie Project. In 2023, a PFS was released that highlighted lithium production across three pad locations from the Prairie Project. In 2024, we partnered with three landowners to secure the three pad locations and immediately went to work permitting and clearing the ground for the pads. A major drilling program was then executed across those three pads, which significantly de-risked the project and put us in a position to continue development toward production. 2025 will be a year of facility construction and commissioning Phase I at Pad #1. Our phased development plan clearly articulates how we will continue to de-risk and develop the project. Modularisation allows rapid and cost-effective scale-up to increase production in Phase II and III.”

About the Prairie Lithium Project

AZL’s Prairie Lithium Project is located in the Williston Basin of Saskatchewan, Canada. Located in one of the world’s top mining friendly jurisdictions, the project has easy access to key infrastructure including electricity, natural gas, fresh water, paved highways, and railroads. The project also aims to have strong environmental credentials, with Arizona Lithium targeting to use less freshwater, land and waste, aligning with the Company’s sustainable approach to lithium development.

Click here for the full ASX Release

This post appeared first on investingnews.com

previous post
Andy Schectman: BRICS, Trump and Gold — What Will Wake the Public Up?
next post
Reinstatement to Quotation

Related Posts

Rapid Critical Metals: Visit us at PDAC 2026...

February 20, 2026

GMV Minerals Inc. Announces Updated PEA Results at...

August 14, 2025

Blackstone Secures New Diamond Drill Rig to Advance...

July 29, 2025

CHARBONE Hydrogen Announces $2M Convertible Debentures Replacement

September 19, 2025

Barrick Backs Hercules in Leviathan-Linked Copper Expansion

July 29, 2025

Locksley Delivers 100% American Made Antimony Ingot

October 20, 2025

SAGA Metals Completes Petrographic Analysis at Drill Ready...

January 20, 2025

Critical One Sells Uranium Assets to Dark Star,...

June 17, 2025

JLL Signs Non-Binding LOI to List McDermitt on...

September 9, 2025

Crypto Market Recap: Cryptos Rally as Trump’s Big...

July 9, 2025

Recent Posts

  • 171 million travelers face airport delays as Democrats’ DHS shutdown hits TSA staffing, Scalise warns
  • FDA launches new AI-powered system to track drug and vaccine side effects nationwide
  • Cornyn reverses on filibuster stance to push Trump’s SAVE Act in Senate
  • DAVID MARCUS: Sen Thune has no idea how mad the GOP base is at him
  • Trump touts 5-0 sweep by endorsed candidates in Tuesday primary elections

Recent Comments

No comments to show.

About Us

About Us

Design Magazine

Welcome to Design Magazine. Follow us for daily & updated design tips, guide and knowledge.

Stay Connect

Facebook Twitter Instagram Pinterest Youtube Email

Recent Posts

  • 171 million travelers face airport delays as Democrats’ DHS shutdown hits TSA staffing, Scalise warns

    March 12, 2026
  • FDA launches new AI-powered system to track drug and vaccine side effects nationwide

    March 12, 2026
  • Cornyn reverses on filibuster stance to push Trump’s SAVE Act in Senate

    March 12, 2026
  • DAVID MARCUS: Sen Thune has no idea how mad the GOP base is at him

    March 12, 2026
  • Trump touts 5-0 sweep by endorsed candidates in Tuesday primary elections

    March 12, 2026
  • US destroys 16 Iranian mine boats as Strait of Hormuz oil showdown escalates

    March 12, 2026

Editors’ Picks

  • 1

    Environmental Approval for Boland Infield Studies & Update on Scaled Column ISR Test

    September 19, 2025
  • 2

    Small Caps are Set to Skyrocket in 2025—Here’s What You Need to Know

    December 12, 2024
  • 3

    Ad revenue should stabilize for media companies in 2025 — if they have sports

    December 31, 2024
  • 4

    Trump leaves China guessing what his next move is with unusual inauguration invitation

    December 15, 2024
  • 5

    Zinc Stocks: 4 Biggest Canadian Companies in 2025

    January 15, 2025
  • 6

    Uranium Price Forecast: Top Trends That Will Affect Uranium in 2025

    December 19, 2024
  • 7

    Lead Price Forecast: Top Trends for Lead in 2025

    January 11, 2025
Promotion Image

banner

Categories

  • Business (630)
  • Investing (3,251)
  • Politics (3,955)
  • Stocks (1,072)
  • About us
  • Contacts
  • Privacy Policy
  • Terms and Conditions
  • Email Whitelisting

Copyright © 2026 bullhedging.com | All Rights Reserved